Worked Example (5 Tasks) ​

Illustrative fixture (duration-weighted, equal calendars):

TaskDuration daysComplete
A10100%
B1050%
C100%
D200%
E100%

Total weight = 60 days. Earned weight = 10 + 5 = 15 → 25% cumulative physical-duration progress (illustrative). Platform series use the worker time-phasing rules for periodization — treat this as intuition, not a substitute for the worker output.