Date Semantics ​

File roleearly_end_date meaningCompleted work
BaselineOriginal planact_end_date
UpdateCurrent forecastact_end_date

The Target Trap ​

Do not use target_end_date for wave/slippage tracking in update files — it is often a static inherited value.